Construction progress
01/04/2020

Construction progress for April 2020

In April 2020, the following works are being performed at the LUCKY LAND construction site:

House No. 3, Section 1:

  • Work is underway on the installation of vertical elements at the +3,800 m mark and the installation of the floor formwork at the +7,500 m mark.

House No. 3, Section 2:

  • Work is underway on the installation of vertical elements at the +3,800 m mark.

House. 3, Section 3:

  • The work on the arrangement of the grid was completed and the wall along the deformation seam was reinforced.
  • The parking grid is 100% complete.

House No. 4:

  • 25% opening of the pit has been completed.