Construction progress
01/04/2020
Construction progress for April 2020
In April 2020, the following works are being performed at the LUCKY LAND construction site:
House No. 3, Section 1:
- Work is underway on the installation of vertical elements at the +3,800 m mark and the installation of the floor formwork at the +7,500 m mark.
House No. 3, Section 2:
- Work is underway on the installation of vertical elements at the +3,800 m mark.
House. 3, Section 3:
- The work on the arrangement of the grid was completed and the wall along the deformation seam was reinforced.
- The parking grid is 100% complete.
House No. 4:
- 25% opening of the pit has been completed.