Construction progress
01/04/2021
Construction progress for April 2021
In April 2021, the following works are being carried out at the construction site of the LUCKY LAND residential complex:
House No. 3, Section 1:
- Completed installation of PVC constructions of residential buildings (12 floors (windows) each).
- Works on noise insulation in apartments and MOT have been completed.
- Works on the installation of engineering communications in apartments and MOT from the 3rd to the 12th floor have been completed.
- The work on the laying of the wiring for the floors of the apartments and the MOT from the 3rd to the 12th floor has been completed.
- Work is being done on the screeds for the apartments and MOT from the 3rd to the 5th floors.
- Work has begun on the insulation of the facade, loggias and cold passages.
- Decks are installed for installation of elevators.
House No. 3, Section 2:
- Completed installation of PVC constructions of residential buildings (12 floors (windows) each).
- Work is being carried out on the rolling of noise insulation before the installation of engineering communications in apartments and MOT.
- Work is underway to install insulation on the superstructure of the roof.
House No. 3, Section 3:
- Completed installation of PVC constructions of residential buildings (on 13th floor (windows)).
- Works on the installation of engineering communications in apartments and MOT from the 2nd to the 13th floor have been completed.
- The work on the laying of floor coverings for electrical wiring in the floors of apartments and MOT from the 2nd to the 13th floor has been completed.
- Works on rolling noise insulation in apartments and MOT have been completed.
Parking:
- The works on the installation of waterproofing and the opening of the ceiling have been completed.
House No. 4, Section 1:
- Work is underway on the arrangement of the vertical elements of the 13th floor.
- Completed brickwork on the 3rd, 4th, 5th, 6th floors. Works are being carried out on floors -1, 7, 8, 9, 10.
- Works on the arrangement of the stylobate part of floors -2 and -1 have been completed.
- Work is underway to install vertical waterproofing of the underground part.
House No. 4, Section 2:
- The floor of the 10th floor is concreted.
- Completed brickwork on the 3rd, 4th, 5th floor. Work is underway on the 6th, 7th, 8th, and 9th floors.
- Works on the arrangement of the stylobate part of floors -2 and -1 have been completed.
- Work is underway to install vertical waterproofing of the underground part.
House No. 4, Section 3:
- Work is underway to install the floor slab on the 2nd floor.
- Works on the arrangement of the stylobate part of floors -2 and -1 have been completed.
- Work is underway to install vertical waterproofing of the underground part.
House No. 6, Section 2:
- Work is underway on the arrangement of the ceiling above the first floor.
- Work is underway to install vertical waterproofing of the underground part.
House No. 6, Section 1:
- Work is underway on the arrangement of the vertical elements of the 2nd floor.
- Work is underway to install vertical waterproofing of the underground part.
House No. 6, parking lot:
- Concreted foundation slab Fm3.
- Construction of vertical elements is underway.
- Work is underway to install vertical waterproofing of the underground part.