Construction progress for December 2020
In December 2020, the following works are being carried out at the construction site of the LUCKY LAND residential complex:
House No. 3, Section 1:
- Work is underway on the installation of PVC structures from the 3rd to the 10th floor (windows are being installed).
- Roof waterproofing is underway.
- Work is underway to install risers K1 and K2.
- Completed works on the installation of power grid risers.
- Works are underway to install waterproofing of the underground part and backfilling.
House No. 3, Section 2:
- Completed works on the installation of power grid risers.
- Work is underway to arrange the brickwork of the 13th floor.
- Work is underway to install K2 risers.
- Roof waterproofing is underway.
- Backfilling and waterproofing of the underground part is under way.
House No. 3, Section 3:
- Work is underway to arrange the brickwork of the 12th floor.
- Completed works on the installation of power grid risers.
- Laying on the roof is being done.
- Backfilling and waterproofing of the underground part is under way.
Parking
- Work is underway to arrange the backfilling of the waterproofing of the underground part and the floor.
House No. 4, Section 1:
- Work is underway to arrange the floor slab of the 5th floor.
House No. 4, Section 2:
- Work is underway to arrange the floor slab of the 3rd floor.
Pit of the sixth turn
- The pit of the sixth stage of construction is 90% open.