Construction progress
01/12/2020

Construction progress for December 2020

In December 2020, the following works are being carried out at the construction site of the LUCKY LAND residential complex:

House No. 3, Section 1:

  • Work is underway on the installation of PVC structures from the 3rd to the 10th floor (windows are being installed).
  • Roof waterproofing is underway.
  • Work is underway to install risers K1 and K2.
  • Completed works on the installation of power grid risers.
  • Works are underway to install waterproofing of the underground part and backfilling.

House No. 3, Section 2:

  • Completed works on the installation of power grid risers.
  • Work is underway to arrange the brickwork of the 13th floor.
  • Work is underway to install K2 risers.
  • Roof waterproofing is underway.
  • Backfilling and waterproofing of the underground part is under way.

House No. 3, Section 3:

  • Work is underway to arrange the brickwork of the 12th floor.
  • Completed works on the installation of power grid risers.
  • Laying on the roof is being done.
  • Backfilling and waterproofing of the underground part is under way.

Parking

  • Work is underway to arrange the backfilling of the waterproofing of the underground part and the floor.

House No. 4, Section 1:

  • Work is underway to arrange the floor slab of the 5th floor.

House No. 4, Section 2:

  • Work is underway to arrange the floor slab of the 3rd floor.

Pit of the sixth turn

  • The pit of the sixth stage of construction is 90% open.