Construction progress
01/02/2021
Construction progress for February 2021
In February 2021, the following work is being carried out at the construction site of the LUCKY LAND residential complex:
House number 3, section 1:
- Work is underway on the installation of PVC structures on the 11th - 12th floors (windows are being installed).
- Roof waterproofing work completed.
- Completed work on the installation of risers K1 and K2.
- Work has begun on the installation of engineering communications for apartments and MZK.
- Works on the installation of power grid risers have been completed.
- Works on waterproofing of the underground part and backfilling have been completed.
House number 3, section 2:
- Works on the installation of power grid risers have been completed.
- Bricklaying work completed.
- Completed work on the installation of risers K1 and K2.
- Roof waterproofing work completed.
- Works on waterproofing of the underground part and backfilling have been completed.
House number 3, section 3:
- Work is underway on the installation of brickwork on the 13th floor.
- Works on the installation of power grid risers have been completed.
- Completed work on the installation of risers K1 and K2.
- Roof waterproofing work completed.
- Works on waterproofing of the underground part and backfilling have been completed.
Parking
- Work is underway on the waterproofing of the ceiling.
House number 4, section 1:
- Work is underway to install the floor slab on the 8th floor.
- Brickwork in progress on the 3rd floor.
House number 4, section 2:
- Work is underway to install the floor slab on the 7th floor.
House number 4, section 3:
- Work is underway on the installation of a floor slab -2 floors.
Parking
- Fm-5, Fm-6 and Fm-8 grillages were made.
House 6 section 6.3 and 6.2:
- Fm-2 foundation slab completed.
- Work has begun on the installation of vertical elements -1 floor.
House 6 section 6.1:
- Reinforcement of the Fm-1 foundation slab is in progress.