Construction progress
01/02/2021

Construction progress for February 2021

In February 2021, the following work is being carried out at the construction site of the LUCKY LAND residential complex:

House number 3, section 1:

  • Work is underway on the installation of PVC structures on the 11th - 12th floors (windows are being installed).
  • Roof waterproofing work completed.
  • Completed work on the installation of risers K1 and K2.
  • Work has begun on the installation of engineering communications for apartments and MZK.
  • Works on the installation of power grid risers have been completed.
  • Works on waterproofing of the underground part and backfilling have been completed.

House number 3, section 2:

  • Works on the installation of power grid risers have been completed.
  • Bricklaying work completed.
  • Completed work on the installation of risers K1 and K2.
  • Roof waterproofing work completed.
  • Works on waterproofing of the underground part and backfilling have been completed.

House number 3, section 3:

  • Work is underway on the installation of brickwork on the 13th floor.
  • Works on the installation of power grid risers have been completed.
  • Completed work on the installation of risers K1 and K2.
  • Roof waterproofing work completed.
  • Works on waterproofing of the underground part and backfilling have been completed.

Parking

  • Work is underway on the waterproofing of the ceiling.

House number 4, section 1:

  • Work is underway to install the floor slab on the 8th floor.
  • Brickwork in progress on the 3rd floor.

House number 4, section 2:

  • Work is underway to install the floor slab on the 7th floor.

House number 4, section 3:

  • Work is underway on the installation of a floor slab -2 floors.

Parking

  • Fm-5, Fm-6 and Fm-8 grillages were made.

House 6 section 6.3 and 6.2:

  • Fm-2 foundation slab completed.
  • Work has begun on the installation of vertical elements -1 floor.

House 6 section 6.1:

  • Reinforcement of the Fm-1 foundation slab is in progress.