Construction progress for February 2023

Lucky Land – the best eco-city in Kyiv, is building and preparing its first home for sale. Preparatory work on the improvement of the home territory is under way 3. Finishing work has begun in common areas. Work is underway on houses 4 and 5 - installation of plumbing and ventilation ducts.


We are grateful to our investors for the timely payment of installments. You support the construction of the project and the country's economy.


Report for February on the construction of the best LUCKY LAND eco-complex:

House No. 3, Section 1:

  • work on the arrangement of external networks B1, K1, K2 is being carried out;
  • work on the construction of external ETR networks is being carried out;
  • device for finishing basement rooms;
  • finishing device entrance group;
  • installation of pumping equipment and water metering unit;
  • arrangement of decoration of common areas;
  • installation of ventilation and smoke removal systems;
  • installation of fire alarm systems;
  • the device of a fire-fighting splinking fire-extinguishing pumping station;
  • device of splinker fire extinguishing systems;
  • installation of equipment in electrical panels;
  • the device of ceramic tiles in MOP.

House No. 3, Section 2:

  • device for finishing basement rooms;
  • installation of ventilation and smoke removal systems;
  • device of splinker fire extinguishing systems;
  • installation of equipment in electrical panels.

House No. 3, Section 3:

  • device for finishing basement rooms;
  • arrangement of decoration of common areas;
  • installation of ventilation and smoke removal systems;
  • device of splinker fire extinguishing systems;
  • installation of equipment in electrical panels.

House No. 4, Section 1:

  • device of ventilation ducts;
  • performance of plumbing works;
  • installation of waterproofing on the terraces and abutment joints between the terraces and facades.

House No. 4, Section 2:

  • device of ventilation ducts;
  • performance of plumbing works;
  • installation of waterproofing on the terraces and abutment joints between the terraces and facades.

House No. 4, Section 3:

  • device of ventilation ducts;
  • performance of plumbing works;
  • the device of waterproofing on the terraces and the junctions between the terraces and facades.

House No. 6, Section 2:

  • installation of interior partitions in apartments;
  • device of ventilation ducts;
  • performance of works on waterproofing of the roof.

House No. 6, Section 1:

  • installation of interior partitions in apartments;
  • device of ventilation ducts.