Construction progress
01/01/2020
Construction progress for January 2020
In January 2020, the following works are being carried out at the construction site of the LUCKY LAND residential complex:
House No. 3:
- As of today, land works on Building No. 3 of the first quarter have already been completed, and land works on Building No. 4 are being carried out.
- The foundation works of sections #1, #2 and #3 have also been completed.
- Work on the foundation of the parking lot will be completed in the near future. Work has begun on arranging the monolithic frame of building No. 3 (section 1, 2, 3).