Construction progress
01/01/2021
Construction progress for January 2021
In January 2021, the following work is being carried out at the construction site of the LUCKY LAND residential complex:
House number 3, section 1:
- Work is underway on the installation of PVC structures from the 3rd to the 10th floors (windows are being installed).
- Roof waterproofing work completed.
- Completed work on the installation of risers K1 and K2.
- Works on the installation of power grid risers have been completed.
- Work is underway to waterproof the underground part and backfill.
House number 3, section 2:
- Works on the installation of power grid risers have been completed.
- Bricklaying work completed.
- Completed work on the installation of risers K1 and K2.
- Roof waterproofing work completed.
- Work is underway on backfilling and waterproofing of the underground part.
House number 3, section 3:
- Work is underway on the installation of brickwork on the 13th floor.
- Works on the installation of power grid risers have been completed.
- Work is underway on the installation of risers K1 and K2.
- Roof waterproofing work in progress.
- Work is underway on backfilling and waterproofing of the underground part.
Parking
- Work is underway to backfill the waterproofing of the underground part and ceiling.
House number 4, section 1:
- Work is underway on the installation of vertical elements of the 6th floor.
House number 4, section 2:
- Work is underway to install the floor slab on the 5th floor.
Parking
- Fm-3 and Fm-9 grillages were made.
- Concrete preparation of Fm-5, Fm-6, Fm-8 was completed.
House 6 section 6.3 and 6.2
- Concrete preparation for the Fm-2 foundation slab has been completed.
- Section 6.1 excavation is 90% open.