Construction progress
01/07/2020
Construction progress for July 2020
In July 2020, the following work is being carried out at the construction site of the LUCKY LAND residential complex:
House number 3, section 1:
- Work is underway on the installation of a reinforced concrete frame on the 8th floor (overlapping above the floor).
- Bricklaying of the basement, 3rd and 4th floors is underway.
House number 3, section 2:
- Work is underway on the installation of vertical elements of the 8th floor.
- Bricklaying is underway on the 3rd and 4th floors. Basement brickwork completed.
House number 3, section 3:
- Work is underway on the installation of vertical elements of the 4th floor.
House number 4:
- The foundation slabs of sections 4.1 and 4.2 were concreted;
- Section 4.3 concrete preparation completed;
- The excavation of the foundation pit for the parking of the 4th stage continues.
Parking:
- Work is underway on the installation of part of the floor slab and vertical elements.