Construction progress
01/07/2021
Construction progress for July 2021
In July 2021, the following works will be carried out at the construction site of the "LUCKY LAND" housing complex:
Building No. 3, Section 1:
- The screed installation work on the MZK 13th floor has been completed.
- Works on insulation and facade decoration are being carried out.
- Installation of elevator equipment is being carried out.
- Installation of apartment switchboards is being carried out.
- Work is being carried out on the installation of fasteners under the stained glass windows of the first floors.
- Installation of PVC structures on cold passages and vestibules has been completed.
- Work is underway to install metal fences on stairwells and cold passages.
- Installation of fire alarm cabling in apartments and office premises has been completed.
Building No. 3, Section 2:
- The screeding work on the apartments and MZK from the 9th to the 13th floor has been completed.
- Works on insulation and facade decoration are being carried out.
- Installation of elevator equipment is being carried out.
- Installation of PVC structures on cold passages and vestibules has been completed.
- Work is underway to install metal fences on stairwells and cold passages.
- Installation of fire alarm cabling in apartments and office premises has been completed.
Building No. 3, Section 3:
- The screeding work on the apartments and MZK from the 3rd to the 11th floor has been completed.
- Works on insulation and facade decoration are being carried out.
- Installation of elevator equipment is being carried out.
- Installation of fire alarm cabling in apartments and office premises has been completed.
- Work is underway to install metal fences on stairwells and cold passages.
Building No. 3, Parking:
- Works on the arrangement of the splinker fire extinguishing system are being carried out.
- Work is being carried out on the installation of fire alarm cabling.
Building No. 4, Section 1:
- The brickwork on the roof has been completed.
- Roof waterproofing is being carried out.
Building No. 4, Section 2:
- The ceiling of the 13th floor is concreted.
- Brickwork is being done on the 12th floor.
- Work is being carried out on the installation of vertical elements of the stylobate part of the 2nd floor.
Building No. 4, Section 3:
- Work is underway to install the vertical elements of the 11th floor.
- Work on the installation of vertical elements of the stylobate part of the 1st floor is being carried out.
- Work is underway to install brickwork from the 3rd to the 7th floor.
Building No. 6, Section 1:
- Work on the arrangement of the floor slab of the 3rd floor is being carried out.
Building No. 6, Section 2:
- Work on the arrangement of the vertical elements of the 4th floor is being carried out.
Building No. 5, Section 1, 2, 3:
- Pit opening works are being carried out.