Construction progress
01/06/2020

Construction progress for June 2020

In June 2020, the following work is being carried out at the construction site of the LUCKY LAND residential complex:

House number 3, section 1:

  • Work is underway on the installation of a reinforced concrete frame of the 6th floor (overlap above the floor);
  • Bricklaying of the basement and 3 floors is underway.

House number 3, section 2:

  • Work is underway on the installation of a reinforced concrete frame of the 6th floor;
  • 3rd floor brickwork in progress.

House number 3, section 3:

  • Work is underway on the installation of a reinforced concrete frame on the 2nd floor.

House number 4:

  • Concrete preparation for the installation of the foundation slab of section 4.1 has been completed;
  • Preparatory work is being carried out on the arrangement of concrete preparation for the foundation slab of section 4.2;
  • Work has begun on the installation of a reinforced concrete foundation slab for section 4.2;
  • Section 4.3 excavation continues.