Construction progress
01/06/2020
Construction progress for June 2020
In June 2020, the following work is being carried out at the construction site of the LUCKY LAND residential complex:
House number 3, section 1:
- Work is underway on the installation of a reinforced concrete frame of the 6th floor (overlap above the floor);
- Bricklaying of the basement and 3 floors is underway.
House number 3, section 2:
- Work is underway on the installation of a reinforced concrete frame of the 6th floor;
- 3rd floor brickwork in progress.
House number 3, section 3:
- Work is underway on the installation of a reinforced concrete frame on the 2nd floor.
House number 4:
- Concrete preparation for the installation of the foundation slab of section 4.1 has been completed;
- Preparatory work is being carried out on the arrangement of concrete preparation for the foundation slab of section 4.2;
- Work has begun on the installation of a reinforced concrete foundation slab for section 4.2;
- Section 4.3 excavation continues.