Construction progress
01/06/2022

Construction progress for June 2022

The Lucky Land comfort-class residential complex is located next to a huge forest and a modern shopping center. This is a real city within a city with developed infrastructure, kindergartens and schools, shops and restaurants, children's and sports grounds.

In June 2022, the following works were performed at the construction site of the Lucky Land residential complex:

Building No. 3, Section 1:

  • Installation of fire doors in technical premises is underway.
  • External network installation works are being carried out.

Building No. 3, Section 2:

  • Execution of works on glazing of the first floors.
  • Installation of fire doors in technical premises is underway.

Building No. 3, Section 3:

  • Completed works on installation of heating radiators in apartments.
  • Installation of fire doors in technical premises is underway.

Building No. 3, parking lot:

  • Works on installation of smoke removal and ventilation systems are being carried out.

Building No. 4, Section 1:

  • Installation of ventilation and smoke removal systems is being carried out.

Building No. 4, Section 2:

  • Installation of PVC constructions of residential floors.

Building No. 4, Section 3:

  • Installation of PVC constructions from the 3rd to the 13th floor is in progress.

Building No. 6, Section 2:

  • Work is being carried out on the installation of brickwork from the 2nd to the 4th floor.

Building No. 5, Section 1, 2, 3:

  • Execution of works on the installation of vertical elements of the first floor of Sections 1 and 2