Construction progress
01/03/2020

Construction progress for March 2020

In March 2020, the following works are being performed at the LUCKY LAND construction site:

  • Building No. 3, section 1. Installation of formwork and concreting of vertical elements at the -0.700 m mark
  • Building No. 3, section 2. Reinforcement, arrangement of formwork and concreting of vertical elements at the mark -1,600 m
  • Building No. 3, section 3. Work on the arrangement of the grillwork was completed and the wall along the deformation seam was reinforced.
  • The parking grid (Fm4) is 100% completed.
  • The parking grid (Fm5) is 100% reinforced.
  • Completed complex of earthworks for the development of the pit for building No. 4 by 25%.