Construction progress
01/03/2021
Construction progress for March 2021
In March 2021, the following works are being carried out at the construction site of the LUCKY LAND residential complex:
Building No. 3, Section 1:
- Installed PVC structures from the 3rd to the 12th floor (windows).
- Work on the installation of engineering communications in apartments and MZK from the 3rd to the 8th floor has been completed.
- Completed work on the installation of electrical wiring in the floors of apartments and MZK from the 3rd to the 7th floor.
- PVC constructions of loggias from the 3rd to the 12th floor (windows) are being installed.
Building No. 3, Section 2:
- Completed works on the installation of power grid risers.
- Finished work on the arrangement of brickwork.
- Completed work on the arrangement of risers K1 and K2.
Building No. 3, Section 3:
- PVC constructions are installed from the 8th to the 13th floor (windows).
- Work is being carried out on the installation of engineering communications in apartments and MZK from the 2nd to the 4th floor.
- Work is being carried out on the installation of electrical wiring in the floors of apartments and MZK from the 2nd to the 4th floor.
Parking
- Work is underway to install waterproofing of the floor.
Building No. 4, Section 1:
- Work is underway to arrange the floor slab of the 10th floor.
- Brickwork is being done on the 3rd and 4th floors.
Building No. 4, Section 2:
- Work is underway to arrange the floor slab of the 9th floor.
- Brickwork is being done on the 3rd and 4th floors.
Building No. 4, Section 3:
- Work is underway to arrange the vertical elements of the 1st floor.
Building 6, section 2
- Work on the arrangement of vertical elements of the -1st floor is being carried out.
Building 6, section 1
- Work is underway on the installation of the floor slab - 1st floor.