Construction progress
01/05/2020
Construction progress for May 2020
In May 2020, the following work is being carried out at the construction site of the LUCKY LAND residential complex:
House number 3, section 1:
- Work is underway on the installation of a reinforced concrete frame of the 4th floor.
House number 3, section 2:
- Work is underway on the installation of a reinforced concrete frame of the 4th floor.
House number 3, section 3:
- Work is underway on the installation of a reinforced concrete frame of the basement floor.
House number 4:
- Excavation work continues.