Construction progress
01/05/2021
Construction progress for May 2021
In May 2021, the following works are being carried out at the construction site of the LUCKY LAND residential complex:
Building No. 3, section 1:
- Completed works on the installation of low current systems for apartments and MOPs from the 3rd to the 12th floor.
- Works on the arrangement of screeds for apartments and MOPs from the 3rd to the 11th floors have been completed.
- Insulation work is being performed facade, loggias and cold transitions.
- Elevator installation work has begun.
- Preparatory work on the screed installation of floors -2 and -1 is underway.
Building No. 3, section 2:
- Completed installation of low current systems in apartments and MOS from the 3rd to the 12th floor.
- Works on installation of heating and water supply wiring are carried out.
- Works on installation of noise insulation in apartments and MOS from the 3rd to 12th floors are carried out.
- Started insulation of the facade, loggias and cold transitions.
- Completed work on the installation of floors for the installation of elevator equipment.
Building No. 3 , section 3:
- Completed works on the installation of low-current systems in apartments and MOS from the 3rd to 12th floors.
- Completed works on the installation of screeds in apartments and MOP from the 3rd to the 5th floor.
- Works are being carried out on the insulation of the facade, loggias and cold transitions.
- Works on the installation of elevator equipment have begun.
Building No. 4, section 1:
- Works are underway on the installation of the technical superstructure floor slab.
- Brickwork has been completed with 3rd to 9th floor. Works are being carried out on -1, 10, 11, 12 floors.
- Works are being carried out on the arrangement of the stylobate part of the floor slab of the 1st floor.
Building No. 4, section 2:
- The floor of the 11th floor has been concreted.
- Brickwork has been completed from the 3rd to the 7th floors. Works are being carried out on -1,8,9,10 floors.
- Works are being carried out on the installation of vertical elements of the stylobate part of the 1st floor.
Building No. 4, section 3:
- Works are being carried out on the arrangement of vertical elements of the 5th floor.
- Works are being carried out on the arrangement of vertical elements of the stylobate part of the 1st floor.
Building No. 6, section 2:
- Works are being carried out on the installation of the floor slab of the second floor .
Building No. 6, section 1:
- Works are being carried out on the installation of the floor slab of the second floor.
Building No. 6, parking lot:
- Concreted foundation slab Fm4.