Construction progress
01/05/2021

Construction progress for May 2021

In May 2021, the following works are being carried out at the construction site of the LUCKY LAND residential complex:

Building No. 3, section 1:

  • Completed works on the installation of low current systems for apartments and MOPs from the 3rd to the 12th floor.
  • Works on the arrangement of screeds for apartments and MOPs from the 3rd to the 11th floors have been completed.
  • Insulation work is being performed facade, loggias and cold transitions.
  • Elevator installation work has begun.
  • Preparatory work on the screed installation of floors -2 and -1 is underway.

Building No. 3, section 2:

  • Completed installation of low current systems in apartments and MOS from the 3rd to the 12th floor.
  • Works on installation of heating and water supply wiring are carried out.
  • Works on installation of noise insulation in apartments and MOS from the 3rd to 12th floors are carried out.
  • Started insulation of the facade, loggias and cold transitions.
  • Completed work on the installation of floors for the installation of elevator equipment.

Building No. 3 , section 3:

  • Completed works on the installation of low-current systems in apartments and MOS from the 3rd to 12th floors.
  • Completed works on the installation of screeds in apartments and MOP from the 3rd to the 5th floor.
  • Works are being carried out on the insulation of the facade, loggias and cold transitions.
  • Works on the installation of elevator equipment have begun.

Building No. 4, section 1:

  • Works are underway on the installation of the technical superstructure floor slab.
  • Brickwork has been completed with 3rd to 9th floor. Works are being carried out on -1, 10, 11, 12 floors.
  • Works are being carried out on the arrangement of the stylobate part of the floor slab of the 1st floor.

Building No. 4, section 2:

  • The floor of the 11th floor has been concreted.
  • Brickwork has been completed from the 3rd to the 7th floors. Works are being carried out on -1,8,9,10 floors.
  • Works are being carried out on the installation of vertical elements of the stylobate part of the 1st floor.

Building No. 4, section 3:

  • Works are being carried out on the arrangement of vertical elements of the 5th floor.
  • Works are being carried out on the arrangement of vertical elements of the stylobate part of the 1st floor.

Building No. 6, section 2:

  • Works are being carried out on the installation of the floor slab of the second floor .

Building No. 6, section 1:

  • Works are being carried out on the installation of the floor slab of the second floor.

Building No. 6, parking lot:

  • Concreted foundation slab Fm4.