Construction progress
01/11/2020
Construction progress for November 2020
In November 2020, the following works are being carried out at the construction site of the LUCKY LAND residential complex:
Building No. 3, Section 1:
- Finished work on the arrangement of the wooden frame.
- Work is underway to arrange the brickwork of the 6th to 13th floors.
- Work is underway to arrange the staircases on the 13th floor.
- Installation of ventilation units is completed.
Building No. 3, Section 2:
- Finished work on the arrangement of the wooden frame.
- Work is underway to arrange the brickwork of the 11th floor.
- Installation of staircases is completed.
- Installation of ventilation units is completed.
Building No. 3, Section 3:
- Finished work on the arrangement of the wooden frame.
- Work is underway to arrange the brickwork of the 7th floor.
- Work is underway to arrange the staircases on the 13th floor.
- Ventilation units have been installed on the 7th floor.
Building No. 4, Section 1:
- Work is underway to arrange the floor slab of the 2nd floor.
Building No. 4, Section 2:
- Work is underway to arrange the vertical elements of the 1st floor.