Construction progress
01/10/2020

Construction progress for October 2020

In October 2020, the following works are being carried out at the construction site of the LUCKY LAND residential complex:

Building No. 3, Section 1:

  • Finished work on the arrangement of the wooden frame.
  • Work is underway to arrange the brickwork of the 3rd to 9th floors.
  • Work is underway to arrange the stairwells of the 9th floor.
  • Installation of ventilation units is completed.

Building No. 3, Section 2:

  • Finished work on the arrangement of the wooden frame.
  • Work is underway to arrange the brickwork of the 11th floor.
  • Work is underway to arrange the staircases on the 11th floor.
  • Ventilation units have been installed up to the 12th floor.

Building No. 3, Section 3:

  • Work is underway to arrange the vertical elements of the 13th floor.
  • Work is underway to arrange the brickwork of the 6th floor.
  • Work is underway to arrange the staircases on the 11th floor.
  • Ventilation units have been installed on the 7th floor.

Building No. 4, Section 1:

  • Work is underway to arrange the vertical elements of the 1st floor.

Building No. 4, Section 2:

  • Work is underway to arrange the vertical elements of floor -1.