Construction progress
01/10/2021

Construction progress for October 2021

The Lucky Land comfort-class residential complex is located next to a huge forest. It is a city within a city with developed infrastructure, kindergartens and schools, shops and restaurants, children's and sports grounds.

In October 2021, the following works will be performed at the construction site of the Lucky Land residential complex:

Building No. 3, Section 1:

• Works on insulation and decoration of the facade are being carried out.

• Plastering of technical premises has been completed.

• Glazing of the first floors is underway.

• The installation of metal fences on stairwells and cold passages has been completed.

• Installation of splinker fire extinguishing systems in basements is being carried out.

• Work on the ventilation and smoke removal system has been completed.

Building No. 3, Section 2:

• Works on insulation and decoration of the facade are being carried out.

• Plastering of technical premises has been completed.

• Glazing of the first floors is underway.

• Installation of metal fences on stairwells and cold passages has been completed.

• Installation of splinker fire extinguishing systems in basements is being carried out.

• Work on the ventilation and smoke removal system has been completed.

Building No. 3, Section 3:

  • Works on insulation and decoration of the facade are being carried out.
  • Plastering of technical premises is being carried out.
  • Work on glazing the first floors has been completed.
  • The installation of metal fences on stairwells and cold passages has been completed.
  • Installation of splinker fire extinguishing systems in basements is being carried out.
  • Works on the ventilation and smoke removal system are being carried out.

Building No. 3, parking lot:

  • Works on installation of the splinker fire extinguishing system are being carried out.
  • Fire alarm cable distribution works are being carried out.
  • Works on installation of smoke removal and ventilation systems are being carried out.
  • Works on the installation of storm sewers have been completed.
  • Works on installation of fire-fighting water supply are being carried out.
  • Works on laying and installation of electricity supply are being carried out.


Building No. 4, Section 1:

  • Installation of PVC constructions from the 3rd to the 13th floor is in progress.

Building No. 4, Section 2:

  • Installation of PVC constructions from the 3rd to the 13th floor is in progress.
  • Roofing work has been completed.

Building No. 4, Section 3:

  • Work is underway to install brickwork on the roof.

Building No. 4, parking lot:

  • Work on the construction of the steel frame has been completed.

Building No. 6, Section 1:

  • Work on the 8th floor ceiling is underway.

Building No. 6, Section 2:

  • Work on the arrangement of the vertical elements of the 9th floor is in progress.

Building No. 5, Section 1, 2, 3:

  • Installation of vertical elements of the underground part of sections 1 and 2 is underway.