Construction progress
01/10/2022

Construction progress for October 2022

LUCKY LAND eco-city is actively growing! Construction work is in full swing, we are erecting facades, laying engineering, carrying out finishing works, preparing for the commissioning of the 3rd building!


LUCKY LAND is the only one, located in a unique location, next to a majestic forest and all the necessary infrastructure. Progressive technological solutions, individual heating, designer lobbies, the highest quality materials, landscaping designed to the smallest detail - all this makes life in LUCKY LAND comfortable and cozy.


Thank you to the brave ZSU, our builders for the opportunity to build in such difficult times for Ukraine. We thank our esteemed investors for their trust and timely payment of installments, each of you makes a significant contribution to the construction of LUCKY LAND.


We share the October report on the construction of the best eco-complex LUCKY LAND:

Building No. 3, section 1:

  • furnishing works are in progress external networks B1, K1, K2;
  • work is being carried out on the installation of external ETR networks;
  • installation of equipment for basement premises;
  • installation of equipment for the entrance group;
  • work on the arrangement of external networks B1, K1, K2 is being carried out;
  • work on the arrangement of external ETR networks is being carried out;
  • arrangement of the equipment of the basement premises;
  • arrangement of the equipment of the entrance group;
  • installation of pumping equipment and water metering unit;
  • installation of ceramic tiles on cold x transitions.

Building No. 3, section 2:

  • arrangement of basement facilities;
  • arrangement of ceramic tiles on cold passages.

Building No. 3, section 3:

  • installation of basement premises;
  • installation of facades;
  • installation of ceramic tiles on cold passages.

Building No. 4, section 1:

  • installation of facades;
  • works are being carried out on the decoration of technical superstructures and ventilation shafts on the roof;
  • installation of elevator equipment.

Building #4, section 2:

  • arrangement of facades;
  • decoration of technical superstructures and ventilation shafts on the roof is in progress.

Building No. 4, section 3:

  • renovation of technical superstructures and ventilation shafts on the roof is underway.

Building No. 6, section 2:

  • work is carried out on laying bricks of ventilation shafts on the roof;
  • waterproofing of the roof is being carried out.

Building No. 6 section 1:

  • the bricklaying of the 8th floor is in progress.