Construction progress
01/09/2020
Construction progress for September 2020
In September 2020, the following work is being carried out at the construction site of the LUCKY LAND residential complex:
House number 3, section 1:
- Work is underway on the installation of a ceiling over the 12th floor;
- Work is underway on the installation of brickwork on the 3rd and 8th floors.
- Work is underway on the arrangement of flights of stairs on the 4th floor.
House number 3, section 2:
- Work is underway on the installation of vertical elements of the 12th floor.
- Work is underway on the installation of brickwork from the 5th to the 8th floor.
- Work is underway on the arrangement of flights of stairs on the 8th floor.
House number 3, section 3:
- Work is underway on the installation of vertical elements of the 10th floor.
- Work is underway on the installation of brickwork on the 2nd and 3rd floors.
- Work is underway on the arrangement of flights of stairs on the 8th floor.
House number 4:
- Work is underway on the device of overlapping over the basement floor.
- The foundation slab was completed in sections 2 and 3.
Parking:
- Reinforced concrete frame work completed.