Construction progress
01/09/2022
Construction progress for September 2022
The beginning of autumn at the construction site of the Lucky Land comfort-class complex, which is located next to an ancient forest and a modern shopping center, was as fruitful as possible.
In September 2022, the following works were performed at the Lucky Land construction site:
Building No. 3, Section 1:
- Performance of works on installation of external networks B1, K1, K2;
- Installation of landscaping near the sales department;
- Installation of equipment of basement premises;
- Installation of ceramic tiles on cold passages and stairwells of evacuation exits;
- Installation of folded roofs on terraces.
Building No. 3, section 2:
- Installation of basement rooms;
- Installation of ceramic tiles on cold passages and stairwells of evacuation exits;
- Installation of a folded roof on the terraces.
Building No. 3, section 3:
- Installation of basement premises;
- Installation of facades.
Building No. 4, section 1:
- Installation of facades;
- Performance of works on installation of decoration of technical superstructures and ventilation shafts on the roof;
- Preparatory works for the installation of elevator equipment.
Building No. 4, section 2:
- Installation of facades;
- Performance of works on installation of decoration of technical superstructures and ventilation shafts on the roof.
Building No. 4, section 3:
- Installation of facades;
- Execution works on arrangement of decoration of technical extras widows and ventilation shafts on the roof.
Building No. 6, section 1:
- Performance of bricklaying works on the 10th floor.
Building No. 6, section 2:
- Performance of brickwork installation from the 3rd to 13th floors.