Construction progress
01/09/2021
Construction progress in the Lucky Land RC in September 2021
A comfort-class residential complex located next to 100 hectares of ancient forest. This is a real city within a city with developed infrastructure, kindergartens and a school.
Building No. 3, Section 1:
- Plastering of technical premises is being carried out.
- Glazing of the first floors is underway.
- Work is underway to install metal fences on stairwells and cold passages.
- Installation of splinker fire extinguishing systems in basements is underway.
- Works on the ventilation and smoke removal system are being carried out.
Building No. 3, Section 2:
- Works on insulation and decoration of the facade are being carried out.
- Plastering of technical premises is being carried out.
- Glazing of the first floors is underway.
- Work is underway to install metal fences on stairwells and cold passages.
- Installation of splinker fire extinguishing systems in basements is underway.
- Works on the ventilation and smoke removal system are being carried out.
Building No. 3, Section 3:
- Works on insulation and decoration of the facade are being carried out.
- Plastering of technical premises is being carried out.
- Glazing of the first floors is underway.
- Work is underway to install metal fences on stairwells and cold passages.
- Installation of splinker fire extinguishing systems in basements is underway.
- Works on the ventilation and smoke removal system are being carried out.
Building No. 3, parking lot:
- Works on the arrangement of the splinker fire extinguishing system are being carried out.
- Fire alarm cabling installation works are being carried out.
- Works on installation of smoke removal and ventilation systems are being carried out.
- Works on the installation of storm sewers are being carried out.
- Works on the arrangement of fire-fighting water supply are being carried out.
- Works on laying and arrangement of electricity supply are being carried out.
Building No. 4, Section 1:
- Installation of PVC structures from the 3rd to the 13th floor is underway.
Building No. 4, Section 2:
- Installation of PVC structures from the 3rd to the 13th floor is underway.
- Roofing works are underway.
Building No. 4, Section 3:
- Work is underway to arrange the brickwork from the 11th to the 12th floor.
Building No. 6, Section 1:
- Work is being carried out on the arrangement of the vertical elements of the 7th floor.
Building No. 6, Section 2:
- Work on the installation of the floor slab of the 7th floor is being carried out.
Building No. 5, Section 1, 2, 3:
- Work on the arrangement of the vertical elements of the underground part of sections 1 and 2 is being carried out.
- The foundation plate of the tower crane is made.